The section of road from Amos Lane junction to near High Street, including the traffic island is going to be resurfaced. Some roads will be closed while the work is carried out, and there will be restricted access into and out of side roads. This should only be for a limited period with clearly marked local diversions  in place.
The working times and dates will be as follows:
Sunday 29th January 8am onwards
Sunday 5th February 9am onwards
Monday 6th to Friday 10th February 6.30pm to Midnight
Some work will include using noisy machinery to take out the existing road surface. The highways agency have apologised in advance for any inconvenience. and ensure residents every effort will be made to keep noise to a minimum and to complete work as early as possible.
Access to frontages will be maintained as far as possible. However at certain times, when work is taking place directly in front of the entrance to your properties  access may be temporarily restricted. Pedestrian access to premises will be maintained. Site staff will be on hand to assist with any difficulties.
For further information please contact Mick Wolverson on 01902 555679 or Khalid Akhtar on 01902 551841.